Here is the chart of our completed & planned activities to complete the van build. Our original timeline was 20 weeks (departure Jan 1), because we were building part-time. The week of September 13, we switched to a full-time build, and we were aiming to be done in 10 weeks (departure Nov 1).
At some point in October we realized that it would be more like 12 weeks, and I just updated it again on October 18 to shift our build timeline to 13 weeks because the kitchen has revealed several more unanticipated build tasks.
There is a daily and a weekly tab on the spreadsheet below. The daily spreadsheet gives details on the activities we completed each day. The weekly tab is updated weekly with the activities that were completed that week, and what we plan to complete the following week.
On the weekly tab, you can scroll down using the scroll bar on the right to see how we are progressing compared to our goal. I am considering us on track if we are within 5% of our progress goal for a given week.